• Improving safety and efficiency by making significant repairs, rebuilds, and replacements to various mechanical, architectural, and electrical infrastructure elements.
• Planning and implementing architectural repairs that involved roof reconstructions to provide waterproofing, window and door sealing, ADA upgrades, and more.
• Handling mechanical repairs that included:
– 4 new custom air handling units / 107 single duct VAVs / new chilled and steam piping from
tunnels / new DDC control tied into BAS / new ductwork on floors 1-5 / new electrical panels
– New heating water system included:
– 1 new shell and tube heat exchanger / 2 new heating hot water pumps / 1 new air/dirt separator
• Replacing and upgrading electrical systems:
– New 1200A panel / new sub panels / new exit lights